Moreton Business Park, Hereford

  • Main Contractor: Roofwise
  • Roof area: 15000 sq. m
  • Wall area: 1500m sq. m

We were employed by Great West 2003 in early 2015 to refurbish Bays 6-10 of Unit C at Moreton Business Park which were originally Ministry of Defence buildings built between the wars.  We were appointed main contractor responsible for the Construction Phase Health & Safety Plan co-ordinating the whole project.

Car Park Elevation before & after refurbishment.

 

 

 

The project involved the complete refurbishment of the superstructure, stripping and disposing of asbestos cement roofing & cladding, glass rooflights, old sliding doors & personnel doors.  An asbestos survey was done and a full structural calculation check of the steelwork was required before the new work could begin.

The roof & walls were re-clad with Kingspan KS1000RW panels, new polycarbonate rooflights were installed & new single ply lined gutters and PVC downpipes were fitted.  The steelwork was jet washed & low level brickwork re-pointed & painted.  New sectional doors &  personnel doors were fitted along with the necessary steelwork alterations.

Our works also included some new drainage works & a new car park which were subcontracted out to specialist firms.

 